Knockdown Rebuild Sydney

Demolish the existing home and build new on your established lot. Full project management from asbestos inspection and DA through demolition and construction to occupation certificate.

Request a Quote

State Property Development manages knockdown rebuilds across Greater Sydney. NSW Builders Licence 355555C. $20M public liability. A knockdown rebuild – demolish the existing house and build a new one on the same lot – is usually chosen when a property’s location is sound but the existing structure isn’t worth renovating. The land value is kept, the house is replaced.

It’s a two-stage construction project that requires coordination between demolition contractors, asbestos assessors, building designers, engineers, certifiers, and builders. We manage all of it under one contract. You deal with Jay, not six separate contractors who point at each other when something doesn’t line up.

The Knockdown Rebuild Process – Step by Step

Building a new home through a knockdown and rebuild project involves several important stages. At State Property Development, we manage the entire process from the initial site assessment through to construction and handover, ensuring a smooth and efficient experience for our clients across Sydney and NSW.

01

Site Assessment & Feasibility

We begin by assessing your property to determine the development potential and identify any planning constraints that may affect the project, including:

  • Zoning and land use controls
  • Floor Space Ratio (FSR)
  • Building height and setback requirements
  • Existing Development Approval (DA) conditions
  • Heritage conservation requirements
  • Flood, bushfire and overland flow overlays
  • Easements and site restrictions
  • Site access and services
02

Asbestos Inspection

For homes constructed prior to 2004, an asbestos inspection is generally required under the NSW Work Health and Safety Regulation 2017. A licensed asbestos assessor will inspect the property and prepare an asbestos report identifying any hazardous materials that require removal before demolition can commence.

03

Design, Planning & Approvals

Our team works with architects, designers and consultants to prepare your new home design and obtain the necessary approvals. Depending on your project, approvals may include:

  • Development Application (DA)
  • Complying Development Certificate (CDC)
  • Demolition approval
  • BASIX / NatHERS compliance
  • Engineering design
  • Stormwater and hydraulic design
  • Other consultant reports where required
04

Asbestos Removal

Where asbestos-containing materials are identified, they will be safely removed by a licensed Class A or Class B Asbestos Removal Contractor in accordance with SafeWork NSW requirements before demolition begins.

05

Demolition

Once all approvals have been obtained and any asbestos has been removed, the existing dwelling is demolished and the site is prepared for construction. A standard residential demolition in Sydney typically takes 2 to 4 weeks, depending on the size of the dwelling, site access and site conditions.

06

New Home Construction

Construction of your new home commences once the site has been cleared and all necessary approvals are in place. The construction timeframe generally ranges from 32 to 52 weeks, depending on factors such as:

  • Home size and floor area
  • Architectural design complexity
  • Structural engineering requirements
  • Site conditions and access
  • Selected finishes and inclusions
  • Weather conditions
  • Authority inspections and approvals

Throughout construction, our experienced project management team keeps you informed at every stage to ensure your new home is delivered to the highest standard.

07

Occupation Certificate & Handover

Once construction has been completed and all mandatory inspections have been successfully passed, the building certifier will issue an Occupation Certificate (OC). The Occupation Certificate confirms that the new home complies with the approved plans, the National Construction Code (NCC), and all relevant building regulations, allowing you to legally occupy your new home.

Once the building has achieved Practical Completion and the Occupation Certificate has been issued by the Principal Certifier, the final payment becomes due in accordance with the building contract. Following receipt of the final payment, we complete the formal handover and provide all relevant warranties, compliance certificates, manuals and project documentation.

What Affects the Cost

Every knockdown rebuild is priced individually – there’s no single figure that applies across different sites and designs. The main factors are:

  • Demolition scope: site access, structure size, and whether asbestos removal is required
  • New home design and size: floor area, storey count, and level of finish selected
  • Site conditions: slope, soil type, and drainage requirements
  • Structural and engineering requirements: driven by the site and design
  • Design, DA/CDC, and certifier fees: vary by council and project complexity

Use our Free Preliminary Building Estimate tool for a ballpark figure based on your project, or contact us directly for a tailored assessment.

Asbestos – What You Need to Know

Any home built before 2004 must have an asbestos survey before demolition work begins. This is not optional – it’s required under the NSW Work Health and Safety Regulation 2017. Friable asbestos (can be crumbled by hand) requires a Class A licensed removalist. Non-friable (bonded) asbestos requires at minimum a Class B removalist. We arrange the asbestos inspection as part of the pre-demolition process and will not allow demolition to proceed without a clearance certificate.

→ Not sure if knockdown rebuild or renovation makes more sense for your property? Ask Jay directly

Disclaimer: All information on this website is indicative only and provided as a general guide. Final construction costs will vary depending on architectural design, structural engineering requirements, hydraulic design, BASIX/NatHERS compliance, geotechnical (soil) reports, site conditions, council or certifier requirements, selected finishes, inclusions, and overall project scope. A detailed quotation can only be provided once all relevant plans, reports, and specifications have been completed and reviewed.

Knockdown Rebuild FAQs

Every knockdown rebuild is individually assessed and priced according to its design, scope, site conditions, and required level of finishes. Demolition scope, new home size and specification, engineering requirements, and council fees all factor in. Get a free preliminary estimate or contact us directly for a tailored figure.

Approximately 14-23 months total from project start to occupation certificate. Design: 8-16 weeks. DA approval: 3-6 months at most Sydney councils. Demolition: 2-4 weeks. New home construction: 32-52 weeks. We give you a realistic programme before contract so you know what you’re committing to.

Yes – mandatory under NSW WHS Regulation 2017 for any building constructed before 2004. A licensed asbestos assessor must inspect before demolition starts. Friable asbestos requires a Class A removalist. Non-friable requires Class B minimum. We arrange the inspection and will not allow demolition without clearance.

Yes. Demolition and new home construction both require approval. A CDC (10-20 days via private certifier) covers both if the new dwelling meets NSW Housing Code standards. A DA (3-6 months at council) is required if the site doesn’t qualify for CDC – common on smaller or irregular lots. We check your site first.

It depends on the existing structure. If the home has extensive asbestos, significant structural issues, a layout that doesn’t respond to renovation, or if the renovation scope exceeds 60% of the rebuild cost – a knockdown rebuild is often more cost-effective and produces a better result. If the structure is sound and the layout can be improved with extensions, major renovation is often better value. We’ll give you an honest assessment of both options. Ask Jay for advice on your specific property.